CPMS Supports Network Rail's Wessex Route Capital Delivery Team

18 December 2019

CPMS supports Network Rail's Wessex Route's Capital Delivery team in the successful delivery of a wide range of complex multi-discipline CP5 and CP6 Enhancement and Renewals projects. We have recently achieved all three Wessex key milestones for Feltham and Ewell West projects, bettering the milestones dates by a total of 115 days!


CPMS seamlessly integrates our project managers, commercial managers and construction managers into the Network Rail team to manage projects on its' behalf.


If you need support in the delivery of infrastructure projects, please get in touch.